After the machine is out of the box to the production site, the front feeding system and the rear receiving station are in the folded state, and need to be manually laid up to be ready for powering. After the flat screws on both sides are removed, the corresponding screw holes are found. Screws, the direction of the screen 4 M8 hexagonal screws, the opposite 2 M8 screws, as shown
2.2 Manual boot state machine books to adjust the edge of the location, so that the edge of the rack parallel to the other gear in the artificial discharge can be used to release the appropriate distance or split open.
2.3 The appropriate adjustment of the upper and lower conveying chain of the compression force (hand-pulled books do not move), set the touch screen interface to adjust the host speed,
調整好書本來料監測電眼時間,一般為2-3秒為宜(正常生產)
Adjust the book material incoming electric eye time, generally 2-3 seconds is appropriate (normal production)
2.3 Manual power-on state Use the hand-held jog switch button to slowly transfer the book, adjust the thickness of the book to make it parallel to the lower support plate, without too tight, the book can move freely better (see below).鎖線裝訂設備 臺歷自動鎖線機
回位彈簧力量大小適當調節合適的力度(如下圖)
The size of the return spring force appropriate to adjust the appropriate force (see below)
2.4 Adjust the feed belt stepless adjuster spacing, according to the boot speed and product needs to adjust the spacing, generally about 2CM is appropriate.